A rear extension costs £1,800–£3,000 per square metre in the UK in 2026, or £36,000–£66,000 for a typical 20m² single-storey build excluding kitchens and bathrooms. The average rear extension lands around £40,000 (MyJobQuote, 2026). London and the South East add 20–50%, pushing a 20m² rear extension to £46,800–£90,000. Depth drives planning: 6m on attached houses and 8m on detached ones fall under permitted development.
How much does a rear extension cost by size?
Rear extension costs scale with the footprint — depth times the width of the house. A 3m-deep extension on a 5m-wide terrace creates 15m² for £27,000–£42,000; a full-width 6m-deep extension on the same house creates 30m² for £54,000–£84,000.
| Rear extension size | Mid-range finished cost (UK, 2026) | Typical build |
|---|---|---|
| 15m² (3m × 5m) | £27,000 – £42,000 | Small rear kitchen extension |
| 20m² (4m × 5m) | £36,000 – £56,000 | Standard kitchen-diner with bi-fold doors |
| 24m² (4m × 6m) | £43,200 – £67,200 | Full-width kitchen-diner on a terrace |
| 30m² (5m × 6m) | £54,000 – £84,000 | Family kitchen-diner with utility |
How much does a 3m rear extension cost?
A 3m-deep rear extension costs £27,000–£42,000 at mid-range spec for a typical 5m-wide house (15m² of new floor), or £35,100–£54,600 in London. On a 6m-wide semi-detached house the same 3m depth creates 18m² and costs £32,400–£50,400. The 3m depth is the classic kitchen extension: deep enough for a run of units plus a dining table, shallow enough to leave a real garden, and inside permitted development with room to spare — you only hit the limit at 6m (attached) or 8m (detached).
Rear Extension Cost Calculator
Set your size, storeys, spec and location for a realistic 2026 range.
How much does a single storey rear extension cost?
A single storey rear extension costs £1,800–£3,300 per m² finished (FMB 2026 band; £1,800–£3,000 for a standard build). A shell-only single storey rear costs £1,300–£1,900 per m² — £26,000–£38,000 for a watertight 20m² that you fit out later. Single storey is the default rear extension: permitted development covers it to 6m or 8m deep, and the roof stays flat or pitched at eaves height. Compare the single storey extension cost guide for the full per-m² and spec breakdown.
How much does a double storey rear extension cost?
A double storey rear extension costs £2,000–£3,200 per m² of ground-floor footprint — roughly £40,000–£50,000+ for a modest two-storey build, or £108,000–£180,000 for a full-width two-storey rear (Checkatrade, 2026). Per square metre of total floor space, double storey beats single storey: the foundations, roof and access scaffolding are shared across two floors. The catch is planning — two-storey rear extensions are limited to 3m depth under permitted development, and upper-floor windows must be obscure-glazed. Most full-width double storey rears need a householder application (£258, England, 2026).
How much does a wraparound extension cost?
A wraparound extension costs £43,200–£87,400 in most of the UK and £60,000–£100,000+ in London. A wraparound combines a rear extension and a side return extension in one L-shaped build, typically adding 25–35m² of open-plan ground floor to a Victorian or Edwardian terrace. The build is cheaper than running the two extensions separately (one set of foundations, one roof, one mobilisation), but it almost always needs full planning permission: the side infill breaks the half-width permitted development limit, and most London boroughs protect terraced streets with Article 4 directions. See the side return cost guide for the infill pricing breakdown.
Do I need permission for a rear extension?
Most rear extensions need no planning permission. Permitted development covers a rear extension up to:
- 6m deep on attached houses, 8m on detached (larger home extension scheme — notify the council for prior approval; neighbours get 21 days to object)
- 4m high, or 3m within 2m of a boundary
- The 50% rule: extensions plus outbuildings cover no more than half the land around the original (1948) house
- Materials matching the existing house; eaves and ridge no higher
Full planning permission is required in conservation areas and Article 4 areas, for listed houses, for two-storey rear extensions beyond 3m deep, and whenever any limit is broken. Two-storey rear extensions under permitted development need obscure-glazed upper windows. A Lawful Development Certificate (£129) proves the build was legal — get one before you sell, not after.
What extra costs come with a rear extension?
Every rear extension carries £4,000+ of fees and statutory costs on top of the build price, and most builder quotes exclude VAT at 20%.
| Extra cost | Typical fee (2026) |
|---|---|
| Architect drawings | £1,500 – £5,000 |
| Structural engineer (calculations + drawings) | £500 – £1,500 |
| Planning application (if needed) | £258 householder (England) |
| Lawful Development Certificate (if permitted development) | £129 |
| Building control | £500 – £1,000 |
| Party wall surveyor (per neighbour, if applicable) | £700 – £1,500 |
| Build-over agreement (Thames Water / drains) | £350 – £600 |
| VAT (20%) — usually excluded from builder quotes | +20% on labour and materials |
What are the labour rates behind a rear extension?
Labour runs 50–60% of a rear extension build. The daily trades behind the per-m² rates (MyJobQuote, 2026):
| Trade | Typical rate (2026) |
|---|---|
| Builder / groundworker | £200 – £280 per day (£20 – £35 per hour) |
| Bricklayer | £180 – £250 per day |
| Carpenter | £180 – £250 per day |
| Plumber | £35 – £45 per hour |
| Electrician (Part P registered) | £50 – £90 per hour |
| Plasterer | £180 – £240 per day |
How long does a rear extension take?
A single-storey rear extension takes 10–16 weeks on site; a double-storey rear takes 16–24 weeks. Design, drawings and approvals add 8–16 weeks before a builder starts, so the full project runs 4–6 months for a single storey build and 6–9 months for double storey.
| Stage | Typical duration |
|---|---|
| Design + structural drawings | 4–8 weeks |
| Prior approval or planning permission | 5–8 weeks (8–13 for full permission) |
| Builder procurement | 2–4 weeks |
| Single-storey rear build | 10–16 weeks |
| Double-storey rear build | 16–24 weeks |
Is 30k enough for a rear extension?
£30,000 builds a basic 15–18m² rear extension outside London — a 3m × 5m kitchen extension at basic spec. After drawings (£1,500–£5,000), building control (£500–£1,000), a party wall notice and 20% VAT land inside the budget, the honest all-in figure is 12–15m². In London, £30,000 buys 8–10m². The shell-only route stretches it: a watertight 15m² shell costs £19,500–£28,500, leaving the fit-out for later.
Is 50k enough for a rear extension?
£50,000 builds a 20m² rear extension at mid-range spec in most of the UK (£36,000–£56,000 build cost) with fees and VAT inside the budget. In London the same 20m² runs £46,800–£72,800, so £50,000 buys a basic finish or a smaller footprint. For the wider size and storeys comparison, see the house extension cost guide.
Frequently asked questions
Is 30k enough for a rear extension?
Yes for a basic 12–15m² rear build outside London after fees and VAT. London: 8–10m². Shell-only stretches £30,000 to a watertight 15m².
Do I need permission for a rear extension?
Most rear extensions fall under permitted development: 6m deep attached, 8m detached, 4m high, with prior approval notification. Conservation areas, Article 4 areas and listed houses need full permission (£258).
Is 50k enough for a rear extension?
Yes — a 20m² mid-range rear extension in most of the UK with fees inside. London: basic finish or smaller footprint.
How much for a 20 square metre extension?
£36,000–£56,000 mid-range UK; £26,000–£38,000 shell-only; £46,800–£72,800 in London mid-range. Add fees £4,000+ and VAT 20%.
How much does a 3m rear extension cost?
£27,000–£42,000 mid-range for a 3m × 5m (15m²) build; £35,100–£54,600 in London. A 3m depth stays well inside permitted development.
How much does a wraparound extension cost?
£43,200–£87,400 UK, £60,000–£100,000+ London. Combines rear + side return in one L-shaped build and almost always needs full planning permission.
How long does a rear extension take?
10–16 weeks on site single storey, 16–24 weeks double storey; 4–6 months total including design and approvals.
How we researched these prices
Every range on this page is cross-checked across three kinds of source, last compared on 18 October 2026:
- Published 2026 price guides — FMB, Checkatrade, MyJobQuote's rear extension cost guide and structural engineers' guides. Where guides disagree we quote the overlapping band, not the outlier.
- Real builder quote structures — rear extension quotes itemise groundworks, structure, glazing, kitchen and finishing allowances; we price each line from published 2026 trade rates, including what quotes exclude (VAT, fees, kitchens).
- Live search data — we re-check current published ranges for rear extension terms monthly, so the figures reflect what builders are quoting now, not last year's averages.
The ranges assume a typical project — a 15–30m² single storey rear extension on a terraced, semi-detached or detached house. Stepped foundations, retained trees or a sloping garden push towards the top of each band.
Prices last checked: 18 October 2026 · Page published: 18 October 2026